Night work may require rock excavation, which will increase the noise levels during this time.

Below is the look ahead to the anticipated construction activities for the next week at the intersection of Wilson Street and River Street. All work is weather permitting.

  • Friday, May 24 — The contractor will complete the pavement patching operations at the intersection of Wilson Street and River Street in preparation of the asphalt resurfacing at the intersection. Vehicle access on Wilson Street will remain open. Single lane closures are possible during this work with flaggers directing traffic through this area. 
  • The city requests that all deliveries for North River Street use State Street for access. There may be times when traffic will not be able to egress or ingress North River Street at Wilson Street when the contractor removes and places the new asphalt pavement.
  • Thursday, May 28, to Friday, May, 31 — The contractor will be completing the concrete curb and sidewalk work in preparation for the final paving surface.

 

WILSON STREET STREETSCAPE

(Batavia Avenue to Island/Shumway Avenue)

Find out what's happening in Bataviawith free, real-time updates from Patch.

Below is a look ahead to the anticipated construction activities for the next week. All work is weather permitting. Thank you for your patience during this work.

Night work

 (9 p.m. Tuesday, May 28, through 7 a.m. Friday, May 31)

  • Monday — Memorial Day Observation: No work.
  • The sanitary sewer replacement work from Batavia Avenue to Water Street will be completed this week.
  • The water main installation will begin this week at the intersection of Wilson Street and Batavia Avenue and will head east to Water Street. This work may require rock excavation, which will increase the noise levels during this time.
  • Vehicle access on Wilson Street will remain open. Single lane closures are possible during this work with flaggers directing traffic through this area.
  • Parking on the north side of the street in this area will be closed during this night work.

Daytime work

(Friday, May 24th and Tuesday, May 28th thru Thursday, May 30th)

Find out what's happening in Bataviawith free, real-time updates from Patch.

  • Friday — Pavement patching of the sanitary sewer utility trench locations between Water Street to Batavia Avenue.  This work will take place after 9am.
  • Monday — Memorial Day Observation: No work.
  • Friday through Thursday — Removal of the trees designated for removal and pavement patching for the underground utility work between Water Street and Batavia Avenue and the installation of the temporary traffic signals will continue at the intersections of Wilson St. & Batavia Ave and Wilson St. and Island/Shumway Ave.
  • Vehicle access on Wilson Street will remain open. Single lane closures are possible during this work with flaggers directing traffic through this area.  There may be some traffic inconveniences between the hours of 9am-3pm.
  • Police and Fire Emergency Responders: Emergency access will remain open at all times.  The contractors have been instructed to stop work and bring all booms on equipment down when emergency vehicles with their sirens on are traveling through the job site.  If there are any questions or concerns regarding emergency access, please make sure to let us know so we can address them.

Project Communications

 

SOURCE: City of Batavia

We’ve removed the ability to reply as we work to make improvements. Learn more here

The views expressed in this post are the author's own. Want to post on Patch?